Interconnection Benefits

New Mexico Interconnection Rule

The state of New Mexico has executed Rule 17.9.568 (PDF), otherwise known as Rule 568. The purpose of this rule is to set forth common interconnection requirements and a common interconnection process based on a common screening process for utilities and interconnection customers to expeditiously interconnect generating facilities.

Bi-Annual Interconnection Report

Twice annual interconnection report submitted to the PRC providing a categorization of application types and key metrics to demonstrate the efficiency of the Interconnection Process.

View Report

Net Metering Benefits (all PV customers)

The state of New Mexico has executed Rule 17.9.570 (PDF), otherwise known as Rule 570, which provides guidelines for metering qualifying facilities. When your solar system is producing electricity, your billing meter will slow down or may actually spin backwards. (A digital meter will show an arrow blinking left.) At the end of the month, PNM will take a reading and compare it to last months reading. If your solar system produced less than what you used, PNM will bill you for the NET difference. If you produced more than what you used, the NET overproduction will be credited to you in one of two ways:

  • SMALL PV PROGRAM (Inverter capacity of 10kW-AC or less): PNM will credit you the NET overproduction as a Cumulative Renewable Energy Credit (in kWh) on the next month¿s bill. These credits never expire and, if your system is large enough, can build up during the year and be used later to reduce PNM bills that are high due to things like summer air conditioning. When you close your account, PNM will pay you for any credits remaining on the account at Rate 12, which your can find on pnm.com/rates.
  • LARGE PV PROGRAM (More than 10kW-AC of inverter capacity): PNM will pay for that NET overproduction based on Rate 12 and the payment will be applied on the same bill. NET overproduction is paid each month unlike the cumulative credit in the Small PV Program. You can find Rate 12 on pnm.com/rates.
  • Interconnecting Non-Qualifying Facilities PNM will interconnect with facilities that generate power using less than 75 percent renewable fuels, referred to as "non-qualifying facilities," as long as those facilities comply with both New Mexico Public Regulation Commission (NMPRC) Rule 17.9.568 or 17.9.569 and PNM Interconnection and Safety Standards for Non-Qualifying Facilities (PDF). PNM is not required, however, to purchase energy from a non-qualifying facility. Energy purchase from a non-qualifying facility would be at PNM's discretion with terms and conditions, including metering options, negotiated case by case.

PNM Interconnection Queue Position

Per NMAC Rule 17.9.568, PNM shall maintain and publicly post a single queue of projects sortable by geographic region and shall update the list one time per month. The list shall be utilized to determine the cost responsibility for upgrades necessary to accommodate interconnection. Click one of the buttons below to view or download the list.

Please note, while not subject to NMAC Rule 17.9.568, additional applications to Interconnect are received by PNM. These projects are also placed in the PNM single queue for studies and cost determination. To view the projects in the SGIP queue, please visit the PNM public Oasis site, click Generation Interconnection-Transmission Delivery folder and Status of System Impact Studies sub-folder on the left hand side of the screen. These projects are added to the queue based on the date in the column "Appl Perfected".

List of Feeders

Queue Position Project Number Feeder
1 INT-48593 SL0017
2 INT-47917 VNBU41
3 INT-47938 ELCE11
4 INT-48247 SCEN11
5 INT-48284 SL0017
6 INT-48281 ELCE11
7 INT-47920 LD0318
8 INT-47947 HOND11
9 INT-48788 TULA14
10 INT-48786 TULA14
11 INT-48789 TULA12
12 INT-48787 TULA13
13 INT-48791 ELCE11
14 INT-48280 HOND11
15 INT-56359 AVIL11
16 INT-59932 STPE13
17 INT-60099 RIHO13
18 INT-60827 SCEN14
19 INT-60887 PROG13
20 INT-60935 SOCO14
21 INT-60891 SNVI13
22 INT-60931 VERA22
23 INT-60910 PROG12
24 INT-60408 VERA22
25 INT-60970 NOBE13
26 INT-60992 PROG11
27 INT-60917 SNVI13
28 INT-61013 LOHO12
29 INT-61014 VERA21
30 INT-61015 VERA11
31 INT-60982 SOPA27
32 INT-61032 UNSE11
33 INT-60986 VERA22
34 INT-60951 VERA22
35 INT-61060 SCEN14
36 INT-61059 STJO13
37 INT-60894 PROG13
38 INT-61081 SCEN12
39 INT-61069 VERA11
40 INT-61092 PROG11
41 INT-60690 TRUM14
42 INT-61056 RITA13
43 INT-61110 LSMO12
44 INT-61011 ELCE11
45 INT-60942 ELCE11
46 INT-61061 IRIS11
47 INT-60944 RIHO13
48 INT-60998 COLI11
49 INT-61057 RITA13
50 INT-61123 A10089
51 INT-61129 SL0017
52 INT-61127 PROG13
53 INT-61105 FOHI12
54 INT-61133 BLRA11
55 INT-60843 PROG13
56 INT-61001 TOME12
57 INT-61114 PROG13
58 INT-57775 MEJI14
59 INT-61122 VERA11
60 INT-61067 TRAM11
61 INT-61143 LSMO12
62 INT-61158 FIST13
63 INT-61151 PROG12
64 INT-61080 PROG11
65 INT-60995 PROG12
66 INT-60336 ORTI13
67 INT-61147 FOHI12
68 INT-61164 TOME12
69 INT-61117 IRIS11
70 INT-61191 VERA24
71 INT-61104 BLRA11
72 INT-61189 COLI11
73 INT-61103 ENHI14
74 INT-61199 A10083
75 INT-60629 MD0011
76 INT-60630 MD0011
77 INT-60327 COAL11
78 INT-61153 FIST13