Image Image Contact PNM | About PNM | PNM News
PNM Logo Image PNM Logo Image

PNM Solar Energy Incentive Program:
Completed Application Terms

To be considered complete, an application for interconnection and/or RECs, must include the following:

  • Application form - Each section of the application must be completed, and the application must be signed and dated by the interconnection customer.
  • Non-refundable application fee - Attach a check made payable to Public Service Company of New Mexico (“PNM”) at the time the application is submitted. Applications without the correct application fee will not be considered or reviewed.
  • One-line electric diagram - A one-line electrical diagram of the solar energy system and its interconnection to the utility system. The one-line electrical diagram must include:
    • Renewable generator ( PV panels or solar thermal electric generator)
    • Inverter (must include manufacturer, model number and VAC rating)
    • Customer generation AC disconnect (must include manufacturer, model number and VAC rating)
    • REC meter
    • Main service panel
    • Billing meter
    • Other (e.g. batteries, transfer switches, DC disconnects, etc.)
  • Site-map - A site map showing the location of equipment listed in the one-line diagram, customer name and address, street designator and compass rose.
  • Specification (“Spec”) sheet - The spec sheet for the inverter.

 