Interconnecting Large Facilities |
||||||||||||||||||||||||||||
| |||||||||||||||||
| |||||||||||||||||
In general:
Detailed process:
1. Download the interconnection application form. You can also request an application for interconnection by contacting PNM.
Interconnection application (.pdf)
Contact PNM
PNM
Customer Generation Programs
Alvarado Square
Albuquerque, N.M. 87158-05102. When your project plans are finalized, complete the application for interconnection and return it along with the application fee to PNM to the address below. An application fee of $50 for qualifying facilities with a design capacity less than 100 kilowatts and $500 for qualifying facilities with a design capacity of 100 kilowatts or greater is required. The application must include a copy of the inverter manufacturer's specification sheet showing the inverter's rating and its listing under UL 1741.
If another form of interconnection protection is used, a list of the protective devices associated with the interconnection and the operating procedure is needed. The application will also need to include a simple one-line diagram of the proposed system. For installations where the customer generation disconnect switch (utility-accessible disconnect switch) is not located adjacent to the PNM metering point, a simple site diagram showing the physical locations of all key components of the system is required. The system one-line and site diagram drawings must identify all major equipment including the inverter, electric service panels, the customer generation disconnect switch and the PNM metering point. These last two items must be clearly labeled on the one-line diagram.
View a sample grid-tie only system one-line diagram (.pdf)
View a sample stand-alone capable system one-line diagram (.pdf)
View a sample site diagram (.pdf)
PNM will not process or approve projects without finalized project plans.
The operating procedure, one-line electrical diagram and, if required, the site diagram are critical components of the application for interconnection and will become part of the Interconnection Agreement. Deficiencies in the operating procedure, one-line diagram and site drawing are the most common cause for delays in PNM's review and approval of an application for interconnection.
If there are any questions or concerns about the application or about the interconnection plans, PNM will contact you or your contractor for clarification to resolve the interconnection concerns. If the application is complete and the interconnection plans are acceptable, PNM will approve the interconnection design.
To avoid unnecessary cost and delay, it is recommend that PNM's approval of the final interconnection design be obtained prior to purchasing material or equipment for the project.
After the application has been approved, PNM will send you two originals of the standard form Interconnection Agreement required by NMPRC Rule 17.9.570. Both originals of this agreement will need to be signed by you, the PNM customer/generator owner who is requesting the interconnection. You then return both of the signed originals to PNM for PNM's signature.
PNM will execute the Interconnection Agreement when all inspections are complete and the generating system has been authorized to commence interconnected operation.
After construction of the generating system is complete and after it has received the final electric inspection from the local building codes authority, you or your contractor will need to contact PNM for an interconnection approval inspection. The purpose of PNM's inspection will be:
- to verify that the facility has been constructed as it is represented in the application and in the Interconnection Agreement
- to verify that the anti-islanding and other interconnection protection of the generator is operational
- to install permanent warning signs, and to verify that a permanent weatherproof copy of the one-line diagram and, if required, a site drawing have been installed at the point of metering
View a drawing tube example for waterproof diagram storage
View a mail slot-style example for waterproof diagram storage
View a permanently affixed label example for waterproof diagram display
PNM interconnection inspections normally can be scheduled within 10 working days of receiving a request.
After the interconnection has passed PNM's inspection, PNM will provide written authorization for you to commence interconnected operations of your system. The written authorization to commence interconnected operation is an attachment to the fully executed Interconnection Agreement.
PNM will return one of the fully executed agreements to you, the customer/generator owner, and PNM will file a copy of the fully executed agreement with the New Mexico Public Regulation Commission.
The generating system may not be operated in parallel with PNM's system without PNM's written authorization to do so.
Metering options
Three general metering options are available under NMPRC rule 17.9.570:
Contact PNM
PNM Interconnection and Safety Standards for Qualifying Facilities (.pdf)
PNM's rate No. 12 (.pdf)
NMPRC rule 17.9.570 (.pdf)